Other Meetings

Other Meetings

Minutes of the Meeting chaired by Member (Power Systems), CEA on 29.01.2025 through Hybrid mode to review the transmission schemes, “North Karanpura generation project of NTPC (ERSS XIX)”, “Evacuation of 4.5 GW RE injection at Khavda P.S. under Phase-II – Part A” and “System strengthening in northern region (NRSS XXXVI)” under the Chairmanship of Member (Power Systems), CEA – reg.

Minutes of the Meeting

Minutes of meeting to review the progress of mapping of intra state transmission projects (transmission lines, transmission towers & Substations) on PM Gati Shakti National Master Plan (NMP) – reg.

Minutes of the Meeting

Minutes of meeting taken by Chief Engineer(PSPM), CEA on 17.02.2025 regarding review of ISTS projects having SCOD/ Anticipated COD from Apr-2025 to Dec-2025 -Reg.

Minutes of the Meeting

Minutes of meeting taken by Chief Engineer(PSPM), CEA on 15.04.2025 on the issues raised by POWERGRID regarding solar park developers’ objections to the line corridor of 765 kV D/C Bhadla-III Bikaner-III Transmission line and line crossing issue raised by APRAAVA with POWERGRID-Reg.

Minutes of the Meeting

Minutes of meeting taken by Member(PS), CEA on 21.02.2025 regarding the issue of Land for 765 kV Ahmedabad – Navsari Transmission Line under Khavda Phase -II Part C transmission scheme and Gati Shakti Cargo Terminal -Reg.

Minutes of the Meeting

Minutes of meeting taken by Chief Engineer(PSPM), CEA on 24.04.2025 to review the Transmission Projects under GEC-I & GEC -II Schemes – regarding

Minutes of the Meeting

Minutes of meeting to review the progress of mapping of intra state transmission projects (transmission lines, transmission towers & Substations) on PM Gati Shakti National Master Plan (NMP) – reg.

Minutes of the Meeting

Minutes of the meeting held under the chairmanship of Member (Power Systems) on 4th December 2024 on the issues raised by RE developers w.r.t. Bikaner-III-Neemrana-II 765kV D/c Transmission lines-reg.

Minutes of the Meeting

Minutes of meeting to review the progress of transmission projects under GEC-I and GEC-II Scheme held under the chairmanship of Chief Engineer (PSPM), CEA through VC on 14-11-2024 -Reg.

Minutes of the Meeting

Meeting to review the progress of Associated Transmission System of Patratu STPP (3x800MW) -Reg.

Minutes of the Meeting

Meeting to review the progress of transmission projects impacting the Available Transfer Capacity (ATC)/ Total Transfer Capacity (TTC) requirement of Maharashtra

Minutes of the Meeting

Meeting to review the progress of intrastate transmission projects matching with construction of ISTS transmission system planned to meet the increasing ATC requirement of Gujarat, transmission projects under Green Energy Corridor- I and transmission projects targeted for FY 2024-25

Minutes of the Meeting

Delay in downstream network for Goa-Tamnar and Nangbibra projects being implemented by M/s Sterlite.

Minutes of the Meeting

Meeting to review NERPSIP and Comprehensive Scheme in Arunachal Pradesh & Sikkim

Minutes of the Meeting

Meeting to review the “Transmission Network Adequacy for the State of Maharashtra”

Minutes of the Meeting

Meeting notice to review the progress of critical transmission lines and substations to be chaired by Member(PS) on 28.08.2019

Meeting Notice

Minutes of the Meeting

Meeting notice to review the progress of Prime Minister Development Package – 2015 (PMDP-2015) for transmission package of J&K Power Department to be chaired by CE(PSPM) on 09.08.2019

Meeting Notice

Minutes of the Meeting

Meeting Notice to review the construction progress of critical transmission projects (transmission lines & Substations associated with HEPs in Uttarakhand, transmission projects in J&K and NTPC’s Thermal Power Project (3X660MW) in Jharkhand)to be chaired by CE(PSPM) on 16.11.2018

Meeting Notice

Minutes of the Meeting

Meeting notice to review RoW (Right of Way) issues in Alipurduar-Siliguri 400 kV D/C Transmission Line to be chaired by CE(PSPM) on 08.10.2018

Meeting Notice

Minutes of the Meeting

Meeting notice to discuss changes in intra state transmission system covered under PMDP-2015 proposed by JKPDD to be chaired by CE(PSPM) on 10.09.2018

Meeting Notice

Minutes of the Meeting

Meeting notice to review the physical progress of Alusteng 220/132/33kV S/S and Alusteng – Zainakote 220kV D/C Transmission Line to be chaired by CE(PSPM) on 06.08.2018

Meeting Notice

Minutes of the Meeting

Meeting notice to rReview the physical progress of Prime Minister Development Package -2015 (PMDP-2015) for transmission projects of J&K to be chaired by CE(PSPM) on 07.08.2018

Meeting Notice

Minutes of the Meeting

Meeting notice to review the physical progress of Srinagar – Leh 220 kV Transmission Line by PGCIL & Alusteng 220/132/33kV S/S and Alusteng – Zainakote 220kV D/C Transmission Line being constructed by JKPDD to be chaired by CE(PSPM) on 20.06.2018

Meeting Notice

Minutes of the Meeting

Meeting notice to review progress of critical transmission lines and substations to be taken by Member(PS), CEA on 29.05.2018 in CEA

Meeting Notice

Minutes of the Meeting

Meeting notice for review meeting regarding slow progress of Bableshwar – Kudus 400 KV D/C line of MSETCL & issue of NOC by GMRT and 220 KV Downstream network from 400 KV Kudus s/s to be taken by Member(PS), CEA on 08.06.2018 in CEA

Meeting Notice

Minutes of the Meeting

Meeting notice to review the progress of Prime Minister Development package for transmission of J&K Power Department-Reg

Meeting Notice & Agenda

Minutes of the Meeting

Meeting Notice to review the progress of transmission system for Delhi area

Meeting Notice & Agenda

Minutes of the Meeting

Minutes of meeting taken by Chief Engineer (PSPM), CEA on 20/02/2018 to review the progress of termination work of Srinagar- Leh 200kV line at Alusteng S/S and transmission network associated with Alusteng S/S

Minutes of the Meeting

Meeting to Review progress of Critical Transmission Projects in WR & SR to be held on 25.01.2018, chaired by Member (PS),CEA

Annexure

Meeting Notice & Agenda

Minutes of the Meeting

Meeting Notice for Mahan – Sipat 400kV D/C line held on 05.01.2018 chaired by Member (PS), CEA

Meeting Notice & Agenda

Minutes of the Meeting

Meeting Notice for meeting on 29.12.2017 at CEA to review the progress of transmission system for Delhi area held on 29.12.2017 & chaired by Member (PS), CEA

Meeting Notice & Agenda

Minutes of Meeting

Meeting notice to review progress of Critical Transmission Projects (NR & ER) held on 06.12.2017 chaired by Member (PS), CEA

Meeting Notice & Agenda

Minutes of Meeting

Meeting notice to review the progress of web portal developed by Ministry of Railway for railway clearances for transmission line crossings held on 06.11.17, chaired by Chief Engineer(PSPM), CEA

Meeting Notice & Agenda

Minutes of Meeting

Minutes of meeting taken by CE(PSPM), CEA on 26.09.2017 in CEA, Sewa Bhawan, New Delhi to review progress of web portal for railway clearances for building transmission lines by Ministry of Railway held on 26.09.2017 chaired by Chief Engineer (PSPM), CEA

Meeting Notice & Agenda

Minutes of Meeting

Minutes of meeting to review the progress of the Babhleshwar-Kudus 400kv D/C transmission line and 400/220kV Kudus substation, ERSS-V and ERSS-XVIII scheme and Teesta -III HEPKishanganj 400kv D/C transmission line held on 04.09.2017 chaired by Member (PS), CEA

Meeting Notice & Agenda

Minutes of Meeting

Minutes of meeting for web portal development by Ministry of Railway for expediting approvals for Railway Clearances for building transmission lines held on 30.06.2017 chaired by Chief Engineer (PSPM), CEA

Meeting Notice & Agenda

Minutes of the Meeting

Minutes of meeting for development of web portal on railway clearances for transmission line crossings. held on 05.06.2017 chaired by Chief Engineer (PSPM), CEA

Meeting Notice & Agenda

Minutes of the Meeting

Minutes of meeting to review the progress of transmisson works covred under (i)Comprehensive Scheme for Strengthening of Transmission & Distribution System in Arunachal Pradesh & Sikkim, (ii) North-Eastern Region Power System Improvement Project ( NERPSIP) for six NER States for strengthening of the intra-State Transmissionand Distribution System & (iii) 220kV Transmission System from Alusteng (Srinagar) to Leh in Jammu & Kashmir (J&K) held on 24.04.2017 chaired by Member (PS), CEA

Minutes of the Meeting

Minutes of the meeting to review the progress of trransmission lines & Substions under the power transmission sysstem for Delhi Area-Reg held on 06.03.2017 chaired by Member (PS), CEA

Meeting Notice & Agenda

Minutes of the Meeting