Power System Project Monitoring Division
Power System Project Monitoring Division - Brief Description
Chief Engineer : Shri Sharvan Kumar
Activity of Power System Project Monitoring Division
- Preparation of annual target for construction of Transmission Projects (transmission lines & substations) of 220kV and above voltage levels in the country
- Monitoring of physical progress of transmission projects included in the target of respective FY to achieve the target.
- Periodical review of ISTS transmission projects awarded through Tariff Based Competitive Bidding.
- Publication of Monthly Reports of Transmission Projects under TBCB, Centrally Funded Transmission Schemes (NERPSIP, COMPREHENSIVE, PMDP & PMRP),transmission line and transformation capacity in substation (both of 220 kV &above) commissioned in respective month and up to the respective month in thecurrent FY, Executive Summary & Growth Summary of Transmission lines andSubstations on CEA website.
- Site visit to assess actual progress of transmission project and related issues.
- Facilitate and support project authorities and executing agencies in resolving issues such as forest clearance, right of ways, civil aviation clearance, Railways Clearance, Power line crossing and National High ways crossing etc. coming in the way of timely completion of transmission schemes.
- Compilation of expenditure incurred under State and Private Sector transmission projects included under NIP (National Infrastructure Pipeline) based on inputs
received from State and Private Transmission Utilities & updation of the same on the IIG portal. - Examination of application seeking Grant of Authorization under Section-164 of the Electricity Act 2003 and sending recommendations to MoP.
- Providing information under RTI Act, providing inputs to Ministry of Power on Parliament Questions, Committees of the Parliament, VIP references etc.
Power System Project Monitoring Division - Reports
Power System Project Monitoring Division - Other Reports
Procedure of approval under Section 164 of Electricity Act 2003
Annual Target For Implementation of Transmission system for the FY 2019-20
Extension of submission of proposal for National Awards for meritorious performance in power sector for 2016-17 & 2017-18 up to 31st January 2019
Transmission Capacity Addition During 12th Plan (2012-17) in India
Result Framework Document (RFD) Achievements November 2017 for Transmission Lines & Substations
Site Visit Report to assess construction progress of OPGC-Jharsuguda 400kV D/C line being implemented by OGPTL-II, Sterlite TPP – Jharsuguda 400kV 2xD/C line being implemented by Sterlite Energy Limited (SEL) and corresponding bays at Jharsuguda being implemented by PGCIL
High Capacity Power Transmission Corridors progress status as on 31.08.2017
Site Visit Report on progress and issues of 400 kV Kudus S/s & 400kV Babhleshwar to Kudus D/C line
Site visit of Brief report on progress of transmission works covered under North-eastern Region Power System Improvement Project (NERPSIP) in Meghalaya and Assam
Minutes of the meeting taken by CE(PSPM), CEA on 11.07.2016 at CEA, Sewa Bhawan to review the progress of Transmission Projects covered in the RFD Program of financial year 2016-17
Result Framework Document (RFD) Achievements June 2016 for Transmission Lines & Substations
Result Framework Document (RFD) Achievements May 2016 for Transmission Lines & Substations
Result Framework Document (RFD) Achievements April 2016 for Transmission Lines & Substations
Result Framework Document (RFD) Programme (2016-17) for Transmission Lines & Substations
Result Framework Document (RFD) Achievements (2015-16) for Transmission Lines & Substations
Result Framework Document (RFD) Achievements (2014-15) for Transmission Lines & Substations
Result Framework Document (RFD)Achievements (2013-14) for Transmission Lines & Substations
Result Framework Document (RFD) Achievements (2012-13) for Transmission Lines & Substations
Funds Requirements for transmission Schemes(12th PLAN)
Transmission Capacity Addition During X Plan and Programme of Construction For XI Plan
Transmission Capacity Addition Programme During 2009-10
Transmission Capacity Addition Programme During 2008-09
Transmission Capacity Addition Programme During 2007-08
Transmission Capacity Addition Programme During 2006-07
Transmission Capacity Addition Programme During 2005-06