Encouraged with the results of R&M/Life Extension works carried out during 7th and 8th Plan, the 9th Plan R&M Programme was taken up in 127 units at 29 thermal power stations. Most of the R&M activities identified under 9th plan programme have been completed.
The economic deigned life of the thermal power units is considered to be 25 years. 25 nos. of thermal units which had already completed their designed life were planned for LE works based on Residual Life Assessment (RLA) studies during the 9th Plan. The LE works on all the units have now been completed.
Sl.No. | Particulars | R&M | LEP |
---|---|---|---|
(i) | Number of thermal power stations covered | 29 | 7 |
(ii) | Number of thermal units covered | 127 | 25 |
(iii) | Expenditure incurred | Rs.850 Crores | Rs.1560 Crores |
(iv) | Total Capacity involved | 17305 MW | 1685 MW |
(v) | Expected capacity after LEP | – | 1741 MW |
(vi) | Average PLF of the units before R&M/LE programme | 61.5% | 46% |
(vii) | PLF anticipated after completion | 63% | 75% |
(viii) | Anticipated additional generation / annum | 2350 MU | 4600 MU |
(ix) | Actual additional generation achieved | 5100 MU | 4600 MU |
(x) | Units on which LE works completed | – | 25 Units |
The details are given in Annexure-III & IV.