R&M programme during 9th plan

Encouraged with the results of R&M/Life Extension works carried out during 7th and 8th Plan, the 9th Plan R&M Programme was taken up in 127 units at 29 thermal power stations. Most of the R&M activities identified under 9th plan programme have been completed.

The economic deigned life of the thermal power units is considered to be 25 years. 25 nos. of thermal units which had already completed their designed life were planned for LE works based on Residual Life Assessment (RLA) studies during the 9th Plan. The LE works on all the units have now been completed.

Sl.No.ParticularsR&MLEP
(i)Number of thermal power stations covered297
(ii)Number of thermal units covered12725
(iii)Expenditure incurredRs.850 CroresRs.1560 Crores
(iv)Total Capacity involved17305 MW1685 MW
(v)Expected capacity after LEP1741 MW
(vi)Average PLF of the units before R&M/LE programme61.5%46%
(vii)PLF anticipated after completion63%75%
(viii)Anticipated additional generation / annum2350 MU4600 MU
(ix)Actual additional generation achieved5100 MU4600 MU
(x)Units on which LE works completed25 Units

The details are given in Annexure-III & IV.