R&M programme during 10th plan

The CEA has identified 106 thermal units in consultation with SEBs/State Generation Corporations for LE during the 10th Plan so as to extend their economical life by another 15-20 years and to recapture /up-rate their capacities by implementing comprehensive R&M schemes based on RLA studies. In addition, another 57 units of 14270 MW capacity which are comparatively new also need some R&M work to sustain/improve their performance.

The salient features of the programme:

Sl.No.Particulars 
(i)Number of thermal power stations32
(ii)Number of thermal units106
(iii)Estimated CostRs.9200 Crores
(iv)Total Capacity involved10413 MW
(v)Average PLF of the units before LE programme49%
(vi)Anticipated PLF after completion75%
(vii)Anticipated additional generation/ annum23700 MU
(vii)Capacity expected after completion of LE works10747 MW

The details are given in Annexure-V.

Sl.No.Particulars 
(i)Number of thermal power stations13
(ii)Number of thermal units57
(iii)Estimated CostRs.977 Crores
(iv)Total Capacity involved14270 MW

The details are given in Annexure-VI.